Elevator assembly
Removed plastic on skins pulled rivets on elevator ribs trim servo bracket almost ready for skins Build hours: 2 Session: 7 Jul 2026, 13:32–15:32 Section: Empennage Continue Reading
-

Elevator assembly
Finished parts prep and primed and clecoed – time to come back and double check before next steps Build hours: 2 Session: 5 Jul 2026, 13:14–15:14 Section: Empennage Continue Reading
-

Parts prep elevator
Peeling deburring ready to prime Build hours: 1.93 Session: 3 Jul 2026, 15:00–16:56 Section: Empennage Continue Reading
-

H/S
Skins on looking good and swing arm assembly complete Build hours: 5.03 Session: 2 Jul 2026, 12:35–17:37 Section: Empennage Continue Reading
-

HS installed wire and checked for distortion
Removed top skin and fitted grommets and a hold-off – checked for distortions before final rivets Build hours: 1.02 Session: 1 Jul 2026, 12:15–13:16 Section: Empennage Continue Reading
-

Cleco on second skin
Learned a bit about skins and forgot to put in a cable so we will be doing this again 🙂 Build hours: 1.95 Session: 30 Jun 2026, 11:28–13:25 Section: Empennage Continue Reading
-

H/S skin prep then Cleco RH skin
Peeled plastic and clecoed skin Build hours: 2.95 Session: 28 Jun 2026, 10:30–13:27 Section: Empennage Continue Reading
-

Horizontal Stabiliser rivets
Last rivets in and now an inspection before the skins go on Build hours: 3 Session: 25 Jun 2026, 14:00–17:00 Section: Empennage Continue Reading
-
Horizontal Stabilizer — Assembly
Builder: Sean Walpole Horizontal stabilizer assembly: clecoed parts together and pulled several rivets while working from the construction manual. Build hours: 5 Continue Reading
-
Horizontal Stabilizer — Deburring & Priming
Builder: Sean Walpole, with Sven Holfelder & Kuven Mudly Horizontal stabilizer parts preparation continued: deburring and priming of HS spar, skin, and bracket parts, with countersink tooling prepped and the construction manual referenced throughout. Parts / Hours: Not specified Build hours: 3.5 Continue Reading